Going underground: Latest photos from Crossrail project under London

1/10 New images have been released by Crossrail reveal the project’s progress as it hits the 60% complete mark. More than 23 miles (nearly 90%) of train tunnels are now complete, with tunnelling due to finish in spring 2015.
Above, train tunnel at Paddington. The new Crossrail station is being constructed directly next to Brunel’s Grade I listed Paddington mainline station. Once complete, the station will be 250 metres long and 30 metres wide and will cater for 70,000 passengers a day.
Picture: Crossrail 2/10 Six of Crossrail’s eight tunnelling machines have now completed their drives. The construction of ten new stations in central and southeast London is more than half complete and the surface works, delivered by Network Rail, are well underway.
Platform tunnels at the new Crossrail Bond Street station. The 260 metre long platforms run parallel to and around 100 metres to the south of Oxford Street. From 2018, 220,000 passengers are expected to use Bond Street London Underground and Crossrail station every day. 3/10 Andrew Wolstenholme, Crossrail Chief Executive said: “Crossrail is being delivered on time and on budget. These fantastic images show the scale of work taking place around the clock beneath the streets of London. We are on schedule to provide London and the South East with a fantastic new railway in 2018.”
Platform tunnels at Tottenham Court Road. Alongside TfL’s upgrade of the existing Tube station, Crossrail is building a new station the length of three football pitches, four storeys below ground. More than 200,000 passengers will use Tottenham Court Road station when Crossrail services start in 2018. 4/10 Platform tunnels at Tottenham Court Road. 5/10 Platform tunnels at the new Farringdon station. When it opens in 2018, Farringdon will be one of the busiest stations in Britain. An estimated 90,000 passengers will use the Crossrail station every day and 150,000 will use the Farringdon interchange that will also encompass London Underground and Thameslink services. 6/10 Platform tunnels at the new Crossrail Bond Street station. 7/10 Machinery in the new platform tunnels for Liverpool Street station. More than 1.5 kilometres of platform and pedestrian tunnels are being created over 40 metres below ground level. 8/10 Platform tunnels at the new Crossrail Bond Street station. 9/10 Platform tunnels at the new Crossrail Bond Street station. 10/10 Tunnelling machine Elizabeth at Whitechapel station. The 150 metre long, thousand tonne machine is one of eight used on Crossrail. With almost 90% of tunnelling complete, Elizabeth is one of just two machines still operational.



   VER TODAS
LAS NOTICIAS

Afiliacion   Afiliación
Formulario Afiliacion ACG   Formularios

   
 

Publicaciones
Noticias Formulario Afiliación
Revista OS15   Plantilla Informe de inspección de talud
Revista OS15
de AMITOS
  ACG
Plantilla Informe de Inspección de Talud
Ver detalle   Ver detalle
El desborde de la represa de Oroville en California obligó a la evacuación de casi 200 mil personas

Santiago’s Subway Will Soon Be The First To Run On Mostly Solar And Wind Power
fastcompany

What's new in AutoCAD Civil 3D 2018
Autodesk

 

Afiliación
Para afiliarse debe completar el formulario de afiliación y cumplir con los requisitos requeridos.
Afiliación
EVENTOS
  • ARTÍCULOS

    de interés Ver detalle


    Artículos
    de Interés

    Ver detalle
  • CONGEO

    Congreso Nacional de Geotecnia Ver detalle


    CONGEO
    Congreso Nacional de Geotecnia
    2018
    Ver detalle
  • Afiliación

    Disfrute de los múltiples beneficios que obtiene al afiliarse a la ACG Ver detalle


    Afiliación
    Múltiples beneficios al
    afiliarse a la ACG
    Ver detalle

Sede de la ACG: Colegio de Ingenieros Civiles, Curridabat
Tel. 2253-5564 / 2234-8789 Ext. 107 - Apartado postal 2346 – 1000 San José
- Acerca ACG
- Afiliación
- Beneficios
- Cuota